Short Answer

How should the line is redesigned to operate at the initial 250 units per day target, assuming that no overtime will be used? What is the efficiency of your new design?

The capacity to create anything with the least level of effort is regarded as efficiency.

See the step by step solution

Step by Step Solution

They should the line is redesigned to operate at the initial 250 units per day target, assuming that no overtime will be used

The cycling duration will have to be lowered if overtime is not used. The following is the maximum cycling duration that will satisfy this rate of production.

The calculation is given below:

The efficiency of the new design

Except for station 6, all existing stations are inside that cycling period position 9. To satisfy the revised processing times, tasks 16, as well as 17, should be spread among two stations mainly due to precedent linkages. To fulfill this cycling duration, just move Work 17 to Slot 10 as well as add one extra worker. This approach is efficient in the following ways.

The efficiency calculations are given below: