Schedule the following activities using CPM:

Activity

Immediate Predecessor

Time (Weeks)

A

_

1

B

A

4

C

A

3

D

B

2

E

C,D

5

F

D

2

G

F

2

H

E,G

3

The project ending explains how the project purpose was met successfully. It encompasses the project's last step, which includes acceptance of the item, an analysis of the results, verification quality, as well as project closure settlement.

See the step by step solution

Step by Step Solution

Critical path completion project

In managing projects, a critical route is the largest series of operations that should be completed on schedule for the project to be finished. Any errors in crucial activities will cause the entire project to be delayed.

Critical path duration

Duration of critical path = 1+4+2+5+3=15

Finish timing of the project = 15 weeks.