What is the process used to ensure that all of the needs for a particular item are calculated at the same time in the MRP process?

Low-level coding

See the step by step solution

Step by Step Solution

Low-level coding

Low-level coding helps in planning the items in the correct order. For the items that have been already planned, the demand is not passed to them. While the processing of production, lots of material is used in producing, it is not important that all the materials are applied in the same amount.

It is used as per the requirement of material. If there is less requirement of material, then low-level code will be given.

Utilization of low-level coding

Low-level coding is used in processing. The items that have 0 low-level proceeds earliest and then so on. In this, the system items proceed only one time.